Our company received a request from Private Agro Company "Vilkhivtsi" for an interior electrical network solution design and implementation. The customer created a transparent technical inquiry demanding to power electric cabinets and connect the aeration fan.
Project manager Oleg Romanets
2 weeks
Performance of work
A key aspect for customer
Compliance with the deadline was fundamental as there were other construction and technical activities.
350 m
Cable runway
1 390 m
Cable was routed
40
Electric cabinets were assembled and disconnected
35
Sensors, terminal plates, and controlling points were disconnected
Cable runway
Cable was routed
Electric cabinets were assembled and disconnected
Sensors, terminal plates, and controlling points were disconnected