"Morgan Furniture" plant in Rivne needed reconstruction of an electrical grid in the existing shop to start a new production. Also, we did electrical work in the new warehouse.
Project manage Volodymyr Tverdokhlib
4-months
Performance of work
A key aspect for customer
Compliance with the deadline was fundamental as there were other construction and technical activities
1 000 m
Cable runway
26 900 m
Cable was routed
20
Electric cabinets were assembled and disconnected
350
Illumination and installations devices were installed
Cable runway
Cable was routed
Electric cabinets were assembled and disconnected
Illumination and installations devices were installed